LNG Plant Optimization | Tilbury LNG Plant

Through FortisBC, Jenmar Concepts was asked to install a backup LNG pump at the FortisBC Tilbury LNG plant. This process began with a PRE-FEED study, which was followed by the FEED for the installation of the pump. Jenmar was the primary consultant on this project and provided all engineering disciplines including structural, process, mechanical, and electrical engineering.

October 2014 – October 2016

Submerged LNG pump/ASME vessel
Instrumentation
Control valves
ASME B31.3 piping
Caesar II pipe stressing
Structural platform
Manways
Electrical controls